Construction began on November 5, 2024, with excavation of the foundations, and wrapped up on March 27, 2025, with the final element installed at the top of the structure. A 120-meter tower built in just 120 working days—an extraordinary achievement for a project of this scale and complexity, particularly given the technical and environmental constraints. Each steel module was assembled with millimeter-level precision. The technical inspection was completed on April 10, with no issues reported.
This exceptional result was made possible by a meticulous planning phase. Preparatory work began in 2019, allowing Rai Way to fully understand the site context, anticipate every potential risk, and build a solid engineering and logistical framework to ensure smooth execution. With 273 tons of steel and a 1,000-cubic-meter concrete base, the new tower is one of the tallest structures Rai Way has ever built—engineered for maximum structural integrity, long-term durability, and operational reliability.